Milestone inspection vs SIRS

Both laws came out of the 2021 Surfside collapse and both apply to condo and co-op buildings of three habitable stories or more. They ask different questions, and boards that plan them together save time and often money.

Fla. Stat. 553.899 and 718.112(2)(g)8 to 9

Get a quote

Side by side

TopicMilestone inspectionSIRS
Question it answersIs the structure safe to occupy?What will the big items cost, and when?
BuildingsCondo and co-op, three habitable stories or moreCondo and co-op, three habitable stories or more
First dueAt age 30, or age 25 where the local agency opts for itBy Dec 31, 2025 for existing condo associations
RepeatsEvery 10 yearsAt least every 10 years
Who performs itFlorida-licensed architect or engineer onlyEngineer, architect, RS or PRA
ScopePhase one visual; phase two testing if deterioration is foundVisual inspection of items a to h, then life, cost and funding plan
Goes toThe local building official and the boardThe board, owners and the state division
Money it drivesRepairs, started within 365 days of a phase two reportMandatory reserves that owners cannot waive

The milestone inspection in brief

Section 553.899 requires a milestone inspection by December 31 of the year a building reaches 30 years from its certificate of occupancy, and every 10 years after. A local enforcement agency may set 25 years instead, for local reasons such as a coastal location. Only a Florida-licensed architect or engineer may perform it.

Phase one is a visual examination of habitable and non-habitable areas. If it finds substantial structural deterioration, phase two follows, which may involve destructive or non-destructive testing. Once a phase two report arrives, repairs must begin within 365 days. The association must notify owners within 14 days of the agency's notice and share the inspector's summary within 45 days of the report.

How one feeds the other

Paragraph (g)8 lets a milestone inspection, or a similar local inspection, completed in the past five years replace the visual inspection part of the SIRS, provided it covers what the SIRS visual inspection needs. The provider still has to estimate remaining lives, replacement costs and the funding plan. Paragraph (g)9 lets an association that has just completed a milestone inspection delay its SIRS for up to two consecutive budget years, so the repairs can be scoped first.

In practice: give the SIRS provider the full milestone report, not only the summary. Phase two findings belong in the SIRS as deferred maintenance under items b and f, with the 365-day repair clock reflected in the funding plan.

Local programs that run alongside

Several counties had their own inspections before the state acted, or set the earlier 25-year trigger. The county pages cover the local rule in each of the main condo markets:

Sources

Get a quote

Three short screens. The building first, then you, then the job.

For
Condo and co-op boards and managers in Florida
Buildings
Three habitable stories or more
Cost to the board
Nothing for the introduction

We are an introduction service, not a SIRS provider. We choose one firm that prepares structural integrity reserve studies in your area, tell you its name, and send your request only after you say yes.

Step 1 of 3

The building

Habitable stories in the tallest building

Buildings of three stories or more

Get a quote